Transmission
Distribution & Retail

Replacement, Reinforcement & Modernisation

We are upgrading our Transmission, Distribution & Retail (TD&R) assets to improve reliability, reduce costs and expand our grid capacity.

Current work

Railway Trail


Trenching will begin from the bridge at Coney Island and continue along the Railway Trail to Fractious Street.


Dates
Start Date: MONDAY, OCTOBER 19, 2020


St. David’s


From the swing bridge roundabout heading into St. David’s until Severns Bridge


Dates
Start Date: MONDAY, JUNE 22, 2020


Ferry Road

Between the East and West Split of Ferry Road and down
 the Hill to Echo Lane and Mullet Bay Road


Dates
Start Date: MONDAY, AUGUST 17, 2020


Hamilton Parish


Fractious Street


Dates
Start Date: MONDAY, JULY 6, 2020


Smith’s Parish


Harrington Sound Road
Between Paynter’s Road and Devil’s Hole Hill


Alternative Routes
To avoid traffic delays, we suggest traveling along South Road or North Shore Road in Smith’s.

Dates
Start Date: May 25th, 2020


UPGRADE PATHS

Thank you for your patience as we upgrade our underground transmission cables. As part of the transmission upgrade project, BELCO is replacing 40% of its current underground transmission cables that are over 50 years old. Nearly 25% of our cables have served Bermuda for over 60 years! These cables and other transmission and distribution assets are well beyond their useful lifespans, causing a higher number of faults, system vulnerability and higher maintenance costs.

GETTING OUR GRID READY FOR LARGE-SCALE RENEWABLES

At this point in time, the grid is limited in its capacity to support large-scale generation from renewable resources. Our old cables and network were designed for central generation; they were not designed to accommodate generation from sources distributed across the network. The transmission cables serve as the backbone of the grid; thus their replacement represents a critical step in moving Bermuda towards its energy future.

TD&R UPGRADE CONSTRUCTION PROJECT

The new cables are being installed in multi-service duct banks that will eliminate the need to dig up the roads for cable replacement in the foreseeable future.

Working closely with Works & Engineering and other utilities, the construction phase has been designed to complement Government’s future water and sewage.

Transmission cable replacements

Critical distribution infrastructure reinforcement

(i.e. schools and cell tower)

Grid modernisation projects, such as Advanced Metering Infrastructure